NEM -  South Australian Interconnector Feasibility Study – Final Report

On 19 November 2010, ElectraNet and AEMO issued a draft report in relation to the joint feasibility study of transmission development options that could economically increase the interconnector transfer capability between South Australia and other National Electricity Market (NEM) load centres.

ElectraNet and AEMO held a stakeholder forum on 30 November 2010 to brief market participants and other interested parties on the outcomes of the feasibility study, and a number of submissions from stakeholders have also been received.

The final report into this feasibility study is now available, and looks at options for upgrading the high voltage transmission lines that connect South Australia to the NEM to facilitate increased opportunities for renewable energy development and provide improved network security for South Australia and neighbouring states.  The report also responds to a range of issues and questions raised by stakeholders in their submissions.

The following reports and information are available:

  • South Australian Interconnector Feasibility Study : Final Report
  • South Australia Interconnector Feasibility Study - Final Network Modelling Report
  • South Australia Interconnector Feasibility Study - Final Market Modelling Report
  • External Peer Review of Draft Report by Oakley Greenwood
  • Feasibility Study Estimates for Transmission Network Extensions by SKM
  • ElectraNet/ AEMO response to stakeholder submissions
  • Copies of submissions made by stakeholders
  • A supplementary results data package

Thank you

Tim George
Executive General Manager
Planning
Australian Energy Market Operator

Rainer Korte
Executive Manager
Network Strategy and Regulatory Affairs
ElectraNet

 

South Australian Interconnector Feasibility Study : Final Report
04 Feb 2011 | filename: 0173-0015.pdf
South Australian Interconnector Feasibility Study : Final Network Modelling Report
04 Feb 2011 | filename: 0173-0016.pdf
South Australian Interconnector Feasibility Study : Final Market Modelling Report
04 Feb 2011 | filename: 0173-0017.pdf
Joint Feasibility Study of additional interconnection to South Australia: External Review of draft report (Oakley Greenwood)
22 Nov 2010 | filename: 0179-0177.pdf
Feasibility Study Estimates for Transmission Network Extensions (Sinclair Knight Merz)
19 Nov 2010 | filename: 0179-0176.pdf
ElectraNet/ AEMO response to stakeholder submissions
04 Feb 2011 | filename: 0173-0018.pdf
SA Interconnector Feasibility Study – Public Forum Presentation
07 Dec 2010 | filename: 0177-0002.pdf

 

SUBMISSIONS

ABB
  AGL
Alinta Energy
  The Clean Energy Council
John Diesendorf
 

Government of South Australia
Attachment : Macquarie Capital Report to the Green Grid Forum


 

 