Part 15B clause 135EA of the National Gas Rules (NGR) set out the scope of activities to be managed under the gas Procedures, and clause 135EB sets out the preconditions required for making Procedures under the NGR.
In essence AEMO may only make or change Procedures if AEMO is satisfied the new Procedure or changed Procedure is consistent with the NGL/NGR and is appropriate having regard to the national gas objective and any relevant Access Arrangement.
AEMO may make Procedures that impact on the management of all aspects associated with the effective operation of a retail gas market that is subject to the NGL/NGR. Procedures have been established for each jurisdiction and provide the detail of the obligations of industry participants for the operation jurisdictional gas retail markets.
The NGR prescribes the process to be used in making (or changing) the gas Procedures. It requires that AEMO establish an "approved process" to be used for this purpose. The approved process is a consultative and inclusive process designed to ensure that any change to the Procedures is developed and implemented with due regard to impacted stakeholder concerns. Any stakeholder is provided the opportunity to participate in the consultation for the development of a Procedure change before AEMO approves any change.
The approved process is used for all Procedures governing gas markets operated by AEMO, and includes the declared wholesale market and all retail gas markets. The ability to change the Retail Market Procedures is defined in Part 15B of the NGR and is covered by the Approved Process.
New South Wales and Australian Capital Territory
Procedures - Current
- Retail Market Procedures (NSW and ACT): version 7 - effective from 26 September 2011
- SCLP Amount Calculation Methodology : version 2.0
- Schedule 1 : Register of Balancing Arrangements as required under Clause 25.4 of Retail Market Procedures (NSW and ACT)
Procedures - Approved Amendments Pending Implementation
Guidelines
For previous versions of documents please contact the AEMO Information Centre
Queensland
Procedures
- Retail Market Procedures (Queensland) v6.0 (Marked up) - effective 1 December 2011
- Retail Market Procedures (Queensland) v6.0 (Clean) - effective 1 December 2011
- Queensland Gas Interface Protocol v5.0 (Marked up) - effective 1 December 2011
- Queensland Participant Build Pack 4 v5.0 (Marked up) - effective 1 December 2011
- Queensland Retail Gas Market Settlements Calendar
- Application for Metering Installation Registration - Gas (Queensland) - 18 Aug 2010
- General Procedure for Interval Meter Notifications - 18 Aug 2010
- Metering Installation Parameter Change Notice (Queensland) - 18 Aug 2010
- AEMO Consumed Energy Scenario (Queensland) v2.0 - Effective 21 Mar 2011
Procedures - Approved Amendments Pending Implementation
- Notice of AEMO decision to approve Retail Market Procedure changes (IN045/10)
- Notice of AEMO decision to approve Retail Market Procedure changes (IN048/10)
- Notice of AEMO decision to approve Retail Market Procedure changes (IN004/11)
- Notice of AEMO decision to approve Retail Market Procedure changes (IN017/11)
- Notice of AEMO decision to approve Retail Market Procedure changes (IN018/11)
- Notice of AEMO decision to approve Retail Market Procedure changes (IN019/11)
- Notice of AEMO decision to approve Retail Market Procedure changes (IN037/10, IN039/10 and IN040/10)
- Notice of AEMO decision to approve Procedure Changes (IN027/11)
Guidelines
AEMO Market Clearing Procedure
This procedure has been established to nominate AEMO’s preferred electronic funds transfer facility for the National Electricity Market, Declared Wholesale Gas Market, Short Term Trading Market, Queensland Retail Market, and other payments cleared by AEMO. The procedure has also been provided to assist participants in establishing and operating routine payment processes, and to provide additional information and references.
For previous versions of documents please contact the AEMO Information Centre
South Australia
Procedures - Current
- Retail Market Procedures (South Australia) : v3.0 (clean) (effective 19 May 2011)
- Retail Market Procedures (South Australia) : v3.0 (change marked) (effective 19 May 2011)
- Notice of effective date - Retail Market Procedures (South Australia) v3.0
- Retail Market Procedures (South Australia) : v2.0 (effective 1 September 2010)
- Recalculation Threshold Values : Clause 301B & 301C (effective 20 Feb 2008)
Procedures - Approved Amendments Pending Implementation
- Notice of AEMO decision for IN032/10 - 01 Apr 2011
- Notice of AEMO decision for IN007/10, IN015/10 and IN047/10 - 21 Mar 2011
- Notice of AEMO decision to approve Retail Market Procedure changes (IN037/10, IN039/10 and IN040/10)
- Notice of AEMO decision to approve Procedure Changes (IN027/11)
For previous versions of documents please contact the AEMO Information Centre
Victoria
Procedures
- Retail Market Procedures (Victoria): Version 2 (clean) - Effective 3 October 2011
- Retail Market Procedures (Victoria): Version 2 (marked up) - Effective 3 October 2011
- Gas Interface Protocol : Version 8 - 30 June 2010
- Consumed Energy Scenarios (Victoria) v7.0 - Effective 21 Mar 2011
Procedures - Approved Amendments Pending Implementation
- Notice of AEMO decision to approve version 12.0 of the Gas Interface Protocol and version 7.0 of the Gas Interface Protocol (Queensland) - IN016-10 and IN007-11 - Effective 12 July 2012
- Notice of AEMO decision to approve Retail Market Procedure changes - IN003/11 and IN014/11
- Notice of AEMO decision to approve Gas Interface Protocol changes (IN013/11)
- Notice of AEMO decision to approve Retail Market Procedure changes (IN019/11)
- Notice of AEMO decision to approve Retail Market Procedure changes (IN037/10, IN039/10 and IN040/10)
- Notice of AEMO decision to approve Procedure Changes (IN027/11)
Guidelines
- MIRN Structure (Victoria) - 24 May 2010
- Hi/Lo Validation Parameters : Worked Example - 24 May 2010
- AEMO Pressure Correction Factors
- Technical guide to Victoria's retail market
- Identification of Victorian Contestable Transfer Points
- Post Code to Heating Value Zone Table
For previous versions of documents please contact the AEMO Information Centre
Retail Market Rules (Western Australia)
Retail Energy Market Company Ltd (REMCo) is the gas market operator in Western Australia and REMCo has appointed AEMO as the Market Operations Service Provider for Western Australia. For current Western Australian gas retail operations, please refer to the REMCo website: http://www.remco.net.au.